Marine Link
Friday, April 19, 2024

Bisso Completes Heavy Lift Projects

Maritime Activity Reports, Inc.

April 23, 2001

Bisso Marine Co., Inc.’s heavy lift crews have completed several projects since the beginning of the year. D/B Cappy Bisso launched a 200-ft. dining vessel in Algiers Canal for Superior Diving Co.

D/C Lilli Bisso lifted and set three 280-ton sections for a 300-ft. oilfield supply tug. The bow, center and stern sections were set on blocks for completion of the vessel by Horizon Shipbuilding of Bayou La Batre, Ala.

Lilli Bisso also lifted a 120-ton quarters module in the Algiers Canal for General Marine Leasing. The Blue Water Industries facility at Port Gibson was the sight of a 500-ton jacket-up lift from barge to shore. A 250-ton deepwater wellhead umbilical control reel was loaded aboard the cable and pipe-laying dynamic positioning ship M/V Stolt Seaway Falcon by Lilli Bisso at the Port of Gulfport, Miss. Seaway Falcon is is part of the BP/Exxon Mobil deepwater Mica/Pampano project. This lift was one of 20 completed in a 12-hour period.

Additionally, Lilli Bisso discharged 16 bundles of 115-ton steam generator coils in the Port of Mobile for an Alabama power plant currently under construction.

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week