Second Phase of Dry Excavation Work on Track
In the first two months of execution, the second dry excavation contract for the Pacific Access Channel (PAC 2) removed 263,246 cubic meters of material. The Mexican-Panamanian consortium Cilsa Panama-Minera Maria started the excavation work March 21 and by April 30, registered 3.2 percent progress.