Marine Link
Tuesday, March 19, 2024

Grounded Bulker Refloated off Oman

Maritime Activity Reports, Inc.

May 21, 2019

(Photo: Resolve Marine Group)

(Photo: Resolve Marine Group)

A bulk cement carrier that ran aground off beaches of Al-Fazayah Beach, Salalah in Oman has been refloated in one piece and without no damage to the environment, said the company behind the salvage operation, Resolve Marine Group.

The partially loaded vessel, RAYSUTT II, departed Port of Salalah in May of last year when the port was evacuated due to adverse weather conditions. The vessel lost headway and steerage and subsequently grounded on on May 26, 2018 on Al- Fazayah Beach, a unique vacation spot which is known for the nesting of endangered sea turtles.

The grounding was devastating to the tourist community and locals as the 5 kilometer long landscape is home to five of the world’s seven species of sea turtle, four of which nest there – the green turtle, the hawksbill, the loggerhead, and the Olive Ridley. All of Oman’s turtles have been classified as endangered with the loggerhead turtle facing extinction. Resolve’s goal was to protect the environment and avoid disturbance of the beaches during turtle nesting season.

At the time of the grounding, the vessel was laden with approximately 6,750mt of dry powdered cement. After the initial responder’s failed attempt to refloat during the Monsoon season, she was defueled and declared as a CTL (Constructive Total Loss).

Later, in November 2018 Resolve Marine Group was awarded the contract for removal and disposal of the vessel and cargo.

Resolve subsequently mobilized two of its specialty owned salvage and wreck removal support vessels, Crane Barge RMG 1000 and Resolve Monarch from Singapore, and the assets arrived in Salalah early January.

By early February 2019, the vessel was successfully patched up and refloated with cargo on board by the Resolve team.

According to Resolve, this method was determined to be the most environmentally sound. The other methods proposed by salvors such as cutting in situ would have posed considerable delays, and the local government was averse to the possibility of operations progressing into the next monsoon season, when weather conditions would have made operations more challenging and threatening to the environment.

The vessel was towed by the Resolve Monarch to the port of Salalah, where the bulk of the cargo was discharged by Resolve. The vessel cement pumping system had to be reactivated and modified so that the cement cargo could be directly discharged into closed road tankers to avoid dust pollution. Special airlifts were designed by Resolve to discharge the holds where the cargo was partially solidified and could not be pumped directly.

For the voyage, seven submersible pumps were set up in the engine room and cargo void spaces with automatic start-up activated by a high-level sensor. The feed was sent to the towing vessel Resolve Monarch by WiFi so that salvors could monitor the status of vessel remotely. This system has been entirely conceptualized and fabricated in house and on site.

The vessel was delivered on April 11 and subsequently recycled.

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week