Marine Link
Friday, December 13, 2024

VIDEO: More Than 100 New Offshore Wind Vessels Needed by 2030 to Meet Demand

Maritime Activity Reports, Inc.

June 30, 2021

Over 100 new offshore wind turbine and foundation installation and maintenance vessels will be required for offshore projects planned over the next decade, as the number of proposed projects grows, but also as the turbines and foundations get larger, meaning the currently available fleet won't be able to install them. What is more, most of the current fleet could become obsolete by 2025. This is according to a new study by World Energy Reports. 

"We see that demand [for the offshore wind vessels by 2030] will not be supplied by the existing fleet. New installation vessels or upgrades of existing vessels are required. This presents a $10 billion-plus opportunity for engineering firms, shipbuilders and conversion yards, equipment suppliers, service providers, and those who finance marine assets," Philip Lewis, Director of Research, World Energy Reports told Offshore Engineer TV's Greg Trauthwein in an interview.

First, per Lewis, the demand for offshore wind vessels, of various types, will be driven by government support linked to energy transition policies and then by off-grid demand to support the electrification of the wider economy. 

"From 32GW of installed capacity at the end of 2020, we forecast a global capacity of 235GW by 2030, of which 226GW is expected to be bottom-fixed," Lewis said.

20,000 new bottom-fixed turbines. Current fleet obsolete by 2025

Lewis says that the bottom-fixed capacity additions through 2030 will be achieved with 20,000 new wind turbine installations. More than 95% of these will be on steel monopiles and jackets.

He also pointed out that future installations would call for new capacities and capabilities, and that almost all of the current fleet of international wind turbine installation vessels (WTIVs) will be technically redundant as installation vessels by 2025, as the wind turbine components grow bigger.

"The speed of technology change has been rapid. From 3-4MW turbines at the beginning of the last decade to 8-10MW turbines today and 12-15MW turbines from 2022-2024. We anticipate that the next evolution of turbine will be 20MW units towards the end of the decade," Lewis said.

Providing color on what the larger turbines mean for installation vessel requirements and capabilities, Lewis said: "Bigger power output comes from the bigger swept area resulting from larger rotor diameters. This means longer and heavier blades. These blades need support by larger hubs and the whole power train in the nacelle will become bigger and heavier.

"A taller and heavier wind turbine tower is a result of the longer blades and heavier components. The tower sits on a foundation that needs to be bigger to support the increased loads from the larger turbine."

According to Lewis, only one of today’s WTIV fleet can install the next generation 12-14MW turbines without upgrading.

Interestingly, a Danish company named Cadeler on Wednesday ordered two next-gen wind turbine installation vessels. Cadeler said that the new X-class wind turbine installation vessels will, per load, be able to transport and install seven complete 15MW turbine sets or five sets of 20+ MW turbines, cutting down the number of trips needed for each project. 



Foundations-only vessels

In the interview, apart from wind turbines, Lewis pointed out the factors impacting the wind turbine foundations. 

While from the top side, they're "affected" by larger turbines, the other factor impacting foundations is water depth, another challenge for installation vessels.

"Simply put, offshore wind farms are moving to deeper waters. The monopile foundations for deeper water large turbine projects are outside the capacities of most of the current installation fleet," Lewis said.

Thus far, per Lewis, foundation installation requirements have been largely satisfied by wind turbine installation vessels, and heavy lift vessels built for the oil & gas sector. However, this is now changing.

"Market requirements are now shifting to purpose-built wind foundation installation vessels capable of handling the largest monopile foundations. More specialized vessels will be required for this purpose," Lewis said.

When it comes to wind turbine foundation installation vessels, one such vessel, to be capable of installing XL monopiles and jackets is currently being built in China for the Norwegian company OHT.

OHT ordered the Alfa Lift on speculation in 2018, and has since secured contracts to install foundations at the world's largest wind farm - the Dogger Bank in the UK.

The 51,087-deadweight-tonne vessel will be moored while work continues on the steel and internal fit-out, including the mechanical completion of systems.  

The Ulstein-designed Alfa Lift will feature a 3,000-tonne main crane, a 10,000+ square meter "smart deck", capable of carrying and installing up to 14 XL monopiles or 12 jackets per voyage and will be able to fully submerge the main deck to a depth of 14.66 meters. The ship will have the capacity to carry cargoes of up to 48,500 tonnes.

Offshore Engineer's Greg Trauthwein recently interviewed Torgeir Ramstad, CEO, OHT, in which Ramstad shared the company's plans and its role in the growing offshore wind market, including the Alfa Lift vessel, as well as future offshore wind plans. 


For more information on WER's International Wind Turbine and Foundation Installation Vessel Market Report, please visit www.worldenergyreports.com or contact Rob Howard at +1 561 732 4368 or Phil Lewis at +44 203-966-2492

Subscribe for
Maritime Reporter E-News

Maritime Reporter E-News is the maritime industry's largest circulation and most authoritative ENews Service, delivered to your Email five times per week