South Stream’s offshore section Set for Construction

Maritime Activity Reports, Inc.

November 18, 2014

 

The Gazprom Management Committee addressed the progress with the South Stream

It was stressed that South Stream gas pipeline project was ready for constructing. This includes the most complicated part of the project – the first and the second strings of the offshore gas pipeline. FEED activities are completed for the offshore section. At present, the project contractor Saipem is engaged in detailed engineering of the submerged trunkline.

Almost 300 thousand tons of pipes have been supplied for the first offshore string. Pipeline sections for the deep-water part are currently being welded in the port of Burgas.